133kV 135kV Three-Phase Power Transformer – High Voltage Substation Equipment
- Primary Voltage Ratings 133kV, 135kV, 138kV or others
- Secondary Voltage Ratings 32.4/13.8/11/10.5/6.6/6.3kV or customized
- H.V. Tap Range ± 8×2.5% HV taps or others
- Type Oil-immersed power transformer
- BIL up to 350kV
- Standards IEEE, ANSI, IEC
- Application high-voltage transmission substations, regional grid interconnections, utility power networks
- Power Rating 135kVA - 25MVA
- Certificate UL, CESI, ISO, KEMA
- Cooling Method ONAN/ ONAF
- Opeartion Step Down & Step Up
Technical Specifications
| Rated Power | 135kVA - 25MVA |
| Rating Primary Voltage | 133kV, 135kV |
| Secondary Voltage |
32.4/13.8/11/10.5/6.6/6.3 kV Customized |
| Frequency | 50/60Hz |
| Vector Group | Dyn11, YD11, YNd11 |
| Winding Material | Aluminum/Copper |
| Efficiency | As IEEE, CAS Std or Customized |
| Impedance Voltage | As IEC |
| Altitude | ≤1,000m or Customized |
| Enclosure material | Mid Steel |
| HV Bushing |
| LV Bushing |
| OLTC/NLTC |
| Lifting hook for complete transformer |
| Name plate |
| Oil temperature |
| Winding temperature |
| Radiators |
| Oil level |
| Pressure relief valve |
| CT |
Customization Optional
Packing and Shipping
The transformer's main body is secured onto a heavy-duty transport frame engineered to support weight distribution and reduce vibration during handling. Stabilization systems, including reinforced bracing and cushioning materials, are applied at critical structural points. Protective wrapping layers and desiccant systems are used to maintain internal dryness and protect insulation components. For extended transport durations or overseas shipment, additional measures such as inert gas filling or vacuum preservation may be applied to safeguard internal conditions.
Transportation methods are selected based on transformer dimensions, route conditions, and delivery destination. Options include flat-rack container shipment, open-top container loading, or break-bulk transport for oversized units. All packing materials comply with international shipping and export standards, including ISPM-15 requirements for wooden components. Clear markings indicate lifting positions, center of gravity, orientation requirements, and safety precautions to ensure correct handling throughout transit.
Each shipment is accompanied by complete documentation, including packing lists, inspection records, quality certificates, test reports, drawings, and operation manuals. Upon arrival, customers receive detailed guidance for unloading, storage, and installation. Optional on-site services such as supervision, oil treatment, reassembly, and commissioning support are available to ensure efficient project execution and reliable transformer commissioning.
Manufacturer Test
Progress test
Progress testing for the 133kV / 135kV Three-Phase Power Transformer is conducted at defined manufacturing stages to maintain strict process control. Incoming materials—including magnetic steel, conductors, insulation components, and insulating oil—are verified for compliance with approved specifications. During core assembly and winding production, inspections focus on dimensional accuracy, mechanical alignment, and insulation placement. The active assembly undergoes controlled drying and vacuum treatment, with continuous monitoring to ensure optimal moisture reduction and insulation readiness.
Intermediate electrical evaluations include continuity checks, winding resistance measurements, and preliminary ratio verification. Tank fabrication is examined for welding integrity, dimensional consistency, and surface protection quality. Pressure and sealing tests are conducted before oil filling to confirm structural tightness. All progress test data are recorded and reviewed to ensure traceability, early detection of deviations, and consistent manufacturing quality prior to final acceptance testing.
Design Tests
All transformers will be tested after finishing the production test items as follows:
♦ Leak testing with pressure for liquid-immersed transformers
♦ Test of transformer oil
♦ Measurement of voltage ratio and check of phase displacement
♦ Measurement of winding DC resistance
♦ Measurement of d. c. Insulation resistance between each winding to earth, and check of the core and frame insulation
♦ Capacitive bushing test
♦ Measurement of dissipation factor (tan δ) of the insulation system capacitances, and determination of capacitances windings-to-earth
♦ Measurement of no-load loss and current at 90%,100%,110% of rated voltage
♦ Operation test on on-load tap-changer
♦ Measurement of short-circuit impedance and load loss
♦ Lightning impulse test
♦ Induced-voltage test with partial discharge measurement
♦ Auxiliary wiring check
♦ Current transformer test
♦ Frequency response analysis test
Transformer Factory Acceptance Test
The Factory Acceptance Test (FAT) for the 133kV / 135kV Three-Phase Power Transformer is performed after complete assembly to validate compliance with contractual specifications and applicable standards. Electrical routine tests include winding resistance measurement, voltage ratio accuracy verification, vector group confirmation, polarity checks, and insulation resistance testing. Dielectric tests, such as applied voltage and induced overvoltage withstand tests, confirm insulation reliability.
Performance assessments evaluate no-load losses, load losses, impedance characteristics, and temperature rise to verify efficiency and thermal stability. Partial discharge testing assesses insulation condition, while impulse testing validates resistance to transient overvoltage events. Mechanical inspections include tank pressure testing, oil leakage checks, cooling system operation verification, and tap changer functionality testing. Oil samples are analyzed for dielectric strength and cleanliness. All FAT results are compiled into a formal report and approved prior to shipment release.
Routine Test - Winding Resistance
Test voltage source (commonly used are 6V, 10V, 20V, 40V or 100V, depending on the equipment model or customer requirements)
Temperature and humidity meter (used to record the ambient temperature and humidity during the test)
Disconnect the electrical connection between the test cable and the equipment to ensure that there is no external current or voltage interference.
Select a suitable voltage range for testing and set the test voltage according to the equipment requirements.
Connect the test equipment to the winding terminals of the device under test, making sure the connections are secure and properly grounded to avoid measurement errors.
Apply Test Voltage:
Select the appropriate test current according to the equipment specifications (such as test current for low-voltage windings, single-phase or three-phase windings).
Winding resistance (usually expressed in units of "Ω")
Test current (A)
Test voltage (V)
Temperature (record the winding temperature before and after the test)
Resistance deviation is between 5% and 10% (warning)
Resistance deviation exceeds 10% (further inspection or corrective action is required)
Application
Technical Advantages
Product Packaging
Related Products
FAQ From Customers
-
What is a Transformer?A transformer is an electrical device used to change the voltage of alternating current (AC). It works on the principle of electromagnetic induction, converting high-voltage current into low-voltage current or low-voltage current into high-voltage current. Transformers are widely used in power transmission, distribution systems, and various electronic devices.
-
What are the main uses of a transformer?The main use of a transformer is voltage conversion. Transformers are used in power transmission systems to help transfer electricity from power plants to consumers. In addition, transformers are also used in electronic devices such as chargers, televisions, power adapters, etc., to adjust the voltage to meet the requirements of different devices.
-
Do you have UL listed?Yes, our transformer has UL listed. We have exported to America many pad mounted transformer,substation transformer and HV.