138kV / 140kV / 150kV Three-Phase Oil-Immersed Power Transformer
- Primary Voltage Ratings 138kV / 140kV / 150kV or others
- Secondary Voltage Ratings 32.4/13.8/11/10.5/6.6/6.3kV or customized
- H.V. Tap Range ± 8×2.5% HV taps or others
- Type Oil-immersed power transformer
- BIL up to 350kV
- Standards IEEE, ANSI, IEC
- Application utility grid expansion projects, industrial power systems, cross-regional interconnection stations
- Power Rating 135kVA - 25MVA
- Certificate UL, CESI, ISO, KEMA
- Cooling Method ONAN/ ONAF
- Opeartion Step Down & Step Up
Technical Specifications
| Rated Power | 135kVA - 25MVA |
| Rating Primary Voltage | 138kV / 140kV / 150kV or others |
| Secondary Voltage |
32.4/13.8/11/10.5/6.6/6.3 kV Customized |
| Frequency | 50/60Hz |
| Vector Group | Dyn11, YD11, YNd11 |
| Winding Material | Aluminum/Copper |
| Efficiency | As IEEE, CAS Std or Customized |
| Impedance Voltage | As IEC |
| Altitude | ≤1,000m or Customized |
| Enclosure material | Mid Steel |
| HV Bushing |
| LV Bushing |
| OLTC/NLTC |
| Lifting hook for complete transformer |
| Name plate |
| Oil temperature |
| Winding temperature |
| Radiators |
| Oil level |
| Pressure relief valve |
| CT |
Customization Optional
Packing and Shipping
The transformer main unit is securely mounted on a heavy-duty transport base engineered to distribute weight evenly and reduce mechanical stress during handling. Stabilizing brackets, shock-absorbing materials, and protective padding are applied at critical points to minimize vibration and impact. Moisture barriers, desiccants, and protective wrapping systems are used to preserve internal insulation conditions. For extended transit periods or overseas shipments, additional measures such as vacuum preservation or inert gas filling may be applied.
Transportation methods are selected based on transformer dimensions, total weight, route conditions, and destination requirements. Shipment options include flat-rack containers, open-top containers, or break-bulk cargo for oversized units. All packing materials comply with international export and shipping regulations, including ISPM-15 standards for wooden packaging. Clear handling instructions, lifting points, center-of-gravity markings, and safety notices are displayed to ensure correct handling throughout transportation.
Each shipment includes a complete set of documentation, such as packing lists, quality certificates, inspection records, test reports, drawings, and operation manuals. Upon arrival at the installation site, detailed guidance for unloading, storage, and installation is provided. Optional on-site technical support, including supervision, oil processing, reassembly, and commissioning assistance, can be arranged to ensure smooth installation and reliable operation.
Manufacturer Test
Progress test
Progress testing for the 138kV / 140kV / 150kV Three-Phase Oil-Immersed Power Transformer is conducted systematically throughout the manufacturing process. Incoming materials—including core steel, winding conductors, insulation materials, and insulating oil—are inspected to verify compliance with approved technical specifications. During core assembly and winding fabrication, inspections focus on dimensional precision, mechanical alignment, and insulation application quality. The active assembly undergoes controlled drying and vacuum treatment, with parameters closely monitored to ensure proper moisture removal and insulation readiness.
Intermediate checks include electrical continuity verification, winding resistance measurements, and preliminary voltage ratio confirmation. Tank fabrication is examined for welding quality, dimensional accuracy, and coating integrity. Pressure and sealing tests are performed prior to oil filling to confirm structural tightness. All progress test results are recorded and reviewed to ensure traceability and early identification of any deviations before final acceptance testing.
Design Tests
All transformers will be tested after finishing the production test items as follows:
♦ Leak testing with pressure for liquid-immersed transformers
♦ Test of transformer oil
♦ Measurement of voltage ratio and check of phase displacement
♦ Measurement of winding DC resistance
♦ Measurement of d. c. Insulation resistance between each winding to earth, and check of the core and frame insulation
♦ Capacitive bushing test
♦ Measurement of dissipation factor (tan δ) of the insulation system capacitances, and determination of capacitances windings-to-earth
♦ Measurement of no-load loss and current at 90%,100%,110% of rated voltage
♦ Operation test on on-load tap-changer
♦ Measurement of short-circuit impedance and load loss
♦ Lightning impulse test
♦ Induced-voltage test with partial discharge measurement
♦ Auxiliary wiring check
♦ Current transformer test
♦ Frequency response analysis test
Transformer Factory Acceptance Test
The Factory Acceptance Test (FAT) for the 138kV / 140kV / 150kV Three-Phase Oil-Immersed Power Transformer is carried out after final assembly to confirm compliance with contractual and international standards. Routine electrical tests include winding resistance measurement, voltage ratio and vector group verification, polarity confirmation, and insulation resistance testing. Dielectric verification is conducted through applied voltage and induced overvoltage withstand tests to assess insulation strength. Performance testing evaluates no-load losses, load losses, impedance characteristics, and temperature rise to verify efficiency and thermal stability. Partial discharge testing assesses insulation quality, while impulse testing confirms the transformer’s ability to withstand transient overvoltage events. Mechanical inspections cover tank pressure testing, oil leakage checks, cooling system operation, and tap changer functionality. Oil samples are analyzed to confirm dielectric strength and cleanliness. All FAT results are compiled into a comprehensive report and approved prior to shipment release.
Routine Test - Leak Test
Voltage source (usually 500V, 1 KV or 2.5 KV, customized according to test requirements)
Temperature and humidity meter
Ground electrode
Properly connect the test equipment (such as a leak detector) to the pipe, container or sealing structure of the device under test.
Apply Test Voltage:
Apply the appropriate test pressure (e.g. 10 bar, 15 bar, etc.) depending on the equipment's operating pressure or test standard.
Applied test pressure
Leakage (can be monitored by flow meter or other equipment)
Time record (to ensure that the test time meets the standard requirements)
Initial pressure and final pressure (if any changes)
Minor leakage (good): Very small leakage is allowed, and it is necessary to judge whether it is qualified according to industry standards.
Application
Technical Advantages
Product Packaging
Related Products
FAQ From Customers
-
What is a Transformer?A transformer is an electrical device used to change the voltage of alternating current (AC). It works on the principle of electromagnetic induction, converting high-voltage current into low-voltage current or low-voltage current into high-voltage current. Transformers are widely used in power transmission, distribution systems, and various electronic devices.
-
What are the main uses of a transformer?The main use of a transformer is voltage conversion. Transformers are used in power transmission systems to help transfer electricity from power plants to consumers. In addition, transformers are also used in electronic devices such as chargers, televisions, power adapters, etc., to adjust the voltage to meet the requirements of different devices.
-
Do you have UL listed?Yes, our transformer has UL listed. We have exported to America many pad mounted transformer,substation transformer and HV.